Question 6

A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points.
Which statement is true regarding this scenario?

Correct Answer:B

Question 7

In a Scrum project, when would a requirement get added to the Product backlog?

Correct Answer:C

Question 8

A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.
What is the elapsed time required to complete the story?

Correct Answer:B

Question 9

A team is estimating story points. They estimate that the story falls between a large (13) and a medium (5) and they assign a story point of 8.
What is this technique called?

Correct Answer:C

Question 10

A large product team features six different teams having ten members each, working on a project that involves four high level features.
How many Product Backlogs should the team have?

Correct Answer:A