Free CAP Exam Dumps

Question 61

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

Correct Answer:C

Question 62

Which of the following techniques are used after a security breach and are intended to limit the extent of any damage caused by the incident?

Correct Answer:D

Question 63

Which of the following administrative policy controls requires individuals or organizations to be engaged in good business practices relative to the organization's industry?

Correct Answer:D

Question 64

Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?

Correct Answer:D

Question 65

Which of the following DoD directives is referred to as the Defense Automation Resources Management Manual?

Correct Answer:B