You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone.
What is the project's schedule performance index?
Correct Answer:D
During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?
Correct Answer:C
Which of the following statements about the authentication concept of information security management is true?
Correct Answer:C
During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?
Correct Answer:B
Which of the following DoD directives defines DITSCAP as the standard C&A process for the Department of Defense?
Correct Answer:B