Question 51

- (Exam Topic 3)
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Correct Answer:B

Question 52

- (Exam Topic 3)
Change requests are an output from which Project Integration Management process?

Correct Answer:A

Question 53

- (Exam Topic 6)
Which of the following tasks focuses on decomposing work packages?

Correct Answer:C

Question 54

- (Exam Topic 1)
A large portion of a projects budget is typically expended on the processes in which Process Group?

Correct Answer:B

Question 55

- (Exam Topic 2)
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

Correct Answer:A