- (Exam Topic 3)
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
Correct Answer:C
- (Exam Topic 3)
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
Correct Answer:C
- (Exam Topic 1)
The number of potential communication channels for a project with 5 stakeholders is:
Correct Answer:A
- (Exam Topic 5)
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
Correct Answer:A
- (Exam Topic 6)
When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?
Correct Answer:A