- (Exam Topic 6)
The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?
Correct Answer:C
- (Exam Topic 1)
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
Correct Answer:C
- (Exam Topic 2)
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
Correct Answer:D
- (Exam Topic 1)
Market conditions and published commercial information are examples of which input to the Estimate Costs process?
Correct Answer:C
- (Exam Topic 6)
The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?
Correct Answer:B