A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?

Correct Answer:D

Question 42

- (Exam Topic 2)
Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Correct Answer:D

Question 43

- (Exam Topic 3)
A project management office manages a number of aspects including the:

Correct Answer:D

Question 44

- (Exam Topic 1)
Which tool or technique is effective in a project in which the deliverable is not a service or result?

Correct Answer:D

Question 45

- (Exam Topic 1)
Which input to the Plan Risk Management process provides information on high-level risks?