Question 46

Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?

Correct Answer:C

Question 47

A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success.
Which of the following risk strategies should the project manager adopt?

Correct Answer:A
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 239

Question 48

When forming a project team, there are a number of phases.
When a project team is productive and effective this phase is known as which of the following?

Correct Answer:C

Question 49

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in ADollar figure.
This type of analysis is an example of which of the following?

Correct Answer:C

Question 50

Which of the following is a characteristics of a matrix organization?

Correct Answer:D