Free PK0-004 Exam Dumps

Question 61

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

Correct Answer:B

Question 62

A project manager is creating the WBS.
In which of the following phases is the project?

Correct Answer:B
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139

Question 63

A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?

Correct Answer:D

Question 64

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.
PK0-004 dumps exhibit
Which of the following represents the cost variance for both project completions?

Correct Answer:C
References:
https://pmstudycircle.com/2012/05/schedule-variance-sv-cost-variance-cv-in-project-cost-management/

Question 65

A project manager is working on the project charter. Which of the following phases does this describe?

Correct Answer:A
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107