A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis.
This type of modeling relies on:
Correct Answer:C
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Correct Answer:C
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231
During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?
Correct Answer:D