A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk. Which of the following should the project manager do NEXT?
Correct Answer:E
A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?
Correct Answer:C
An organization has determined that all projects must use a remote dashboard to allow portfolio management. Which of the following would enforce this directive?
Correct Answer:A
The PMO is responsible for: (Choose two.)
Correct Answer:CD
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 85
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
Correct Answer:A
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200