Free PMI-001 Exam Dumps

Question 76

The following is a network diagram for a project.
The total float for the project is how many days?

Correct Answer:A

Question 77

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

Correct Answer:A

Question 78

Schedule milestones and a predefined budget are examples of:

Correct Answer:A

Question 79

Which items are components of a project management plan?

Correct Answer:A

Question 80

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

Correct Answer:B