Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
Correct Answer:C
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
Correct Answer:B
Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
Correct Answer:A
When is a project finished?
Correct Answer:C
The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:
Correct Answer:D