Question 126

Which of the following is a schedule network analysis technique that takes limited resources into account?

Correct Answer:B

Question 127

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

Correct Answer:C

Question 128

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Correct Answer:A