Question 51

- (Topic 5)
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

Correct Answer:A

Question 52

- (Topic 5)
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Correct Answer:B

Question 53

- (Topic 1)
A large portion of a projects budget is typically expended on the processes in which Process Group?

Correct Answer:B

Question 54

- (Topic 1)
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

Correct Answer:B

Question 55

- (Topic 2)
A project manager who communicates to the project team though email is using which type of communication?

Correct Answer:B