Question 86

- (Topic 1)
Identify Risks is part of which Process Group?

Correct Answer:A

Question 87

- (Topic 1)
The Perform Integrated Change Control process occurs in which Process Group?

Correct Answer:C

Question 88

- (Topic 3)
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

Correct Answer:D

Question 89

- (Topic 4)
Which tool or technique is used in Manage Stakeholder Expectations?

Correct Answer:B

Question 90

- (Topic 3)
Plan Risk Management is the process of defining how to:

Correct Answer:B