- (Topic 3)
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
Correct Answer:A
- (Topic 4)
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Correct Answer:D
- (Topic 1)
A technique used to determine the cause and degree of difference between baseline and actual performance is:
Correct Answer:B
- (Topic 1)
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
Correct Answer:C
- (Topic 3)
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
Correct Answer:D