- (Topic 1)
The Perform Quality Assurance process occurs in which Process Group?
Correct Answer:A
- (Topic 2)
The process of defining how the project scope will be validated and controlled is known as:
Correct Answer:C
- (Topic 2)
The following is a network diagram for a project.
The free float for Activity E is how many days?
Correct Answer:C
- (Topic 5)
Which of the following is a project constraint?
Correct Answer:D
- (Topic 2)
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
Correct Answer:C