Free PMI-100 Exam Dumps

Question 11

- (Topic 2)
Technical capability, past performance, and intellectual property rights are examples of:

Correct Answer:B

Question 12

- (Topic 5)
Risk exists the moment that a project is:

Correct Answer:B

Question 13

- (Topic 4)
Which of the following is an input to Develop Human Resource Plan?

Correct Answer:D

Question 14

- (Topic 3)
Which defines the portion of work included in a contract for items being purchased or acquired?

Correct Answer:D

Question 15

- (Topic 4)
Which process involves identifying and documenting the logical relationships between project activities?

Correct Answer:B