Free PMI-100 Exam Dumps

Question 21

- (Topic 1)
Which document describes the necessary information to determine if a project is worth the required investment?

Correct Answer:D

Question 22

- (Topic 5)
An input to the Collect Requirements process is the:

Correct Answer:A

Question 23

- (Topic 2)
Which enterprise environmental factors may influence Plan Schedule Management?

Correct Answer:D

Question 24

- (Topic 4)
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Correct Answer:D

Question 25

- (Topic 2)
Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Correct Answer:D