- (Topic 5)
At the end of the project, what will be the value of SV?
Correct Answer:B
- (Topic 5)
A project manager has created an issue log to document issues communicated by project
team members during weekly team meetings. This is an input of:
Correct Answer:A
- (Topic 3)
A procurement management plan is a subsidiary of which other type of plan?
Correct Answer:B
- (Topic 4)
Which of the following are outputs of Develop Project Team?
Correct Answer:D
- (Topic 4)
Which of the following is an input to Control Scope?
Correct Answer:D