Since the last iteration, the team has grown from six members to 14 members. As a result, in the current iteration, the team room is crowded and uncomfortable during the team's daily standup. It takes the team longer than the ideal amount of time to complete their standup, which creates problems for the team's current schedule. Based on this information, the project manager should:
Correct Answer:B
Which tool allows the Product Owner to focus on providing the greatest value and Return on Investment (ROI) to the organization?
Correct Answer:B
What are three processes used to begin an Agile project?
Correct Answer:B
The ScrumMaster and the Product Owner disagree on the value of a Product Backlog item. In order to resolve the disagreement, the first step the ScrumMaster should take is to ask:
Correct Answer:A
Which technique is used by a project team to estimate the amount of work that can be done per iteration?
Correct Answer:A