Free PMI-SP Exam Dumps

Question 31

You're a project manager and you've completed your project schedule. The schedule will take 18 months to complete the project work. Throughout the schedule there are instances that the project work will require the project team members to work more than fifty hours per week. If you must adhere to a maximum of 45 hours of project work per team member, per week, what will likely happen to your project schedule as it stands right now?

Correct Answer:B
If a resource leveling heuristic, such as 45 hours maximum per time period, is enforced on the project, then the project schedule will take longer to complete. What is resource leveling heuristics? Resource leveling heuristics is a prioritization method that allocates inadequate resources to critical path activities first. It is a schedule network analysis technique useful to a schedule that has already been analyzed by the critical path method. It is used when shared or critical essential resources are only available at certain times, in limited quantities, or to keep resource usage at a constant level. It is a technique that resolves resource conflicts by delaying tasks within their slack allowances. Resource leveling is the process in which project teams come across problems when developing their project schedules. If a company has multiple projects running simultaneously that require the same resources, then problems can arise. It can often cause the critical path method to change.
Answer option A is incorrect. The 45-hour limit is a restriction on the project.
Answer option C is incorrect. The project will not take less time to complete because the project team members won't be able to complete as much work in the same amount of time.
Answer option D is incorrect. The project may require more resources if the project manager and management want the project to finish by a particular date. In this question, however, the focus is on what will happen to the project schedule, not the project staffing.

Question 32

Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method to classify the stakeholders based on their level of authority and their level of concern regarding the project outcomes. This model will help Anna determine the communication demands and when information should be distributed. What does Anna want to create in this instance?

Correct Answer:A
Anna needs to create a power/interest grid. This grid groups the stakeholders based on their level of authority and level of concern regarding the project outcomes. The
power/interest grid forms a group of the stakeholders based on their level of authority (power) and their level of interest in the project. Interest accounts to what degree the stakeholders are affected by examining the project or policy change, and to what degree of interest or concern they have about it. Power accounts for the influence the stakeholders have over the project or policy, and to what degree they can help to accomplish, or block, the preferred change. Stakeholders, who have high power and interests associated with the project, are the people or organizations that are fully engaged with the project. When trying to generate strategic change, this community is the target of any operation.
Answer option B is incorrect. A salience model classifies stakeholders based on their power, urgency, and legitimacy.
Answer option C is incorrect. A power/influence grid groups the stakeholders based on their power and influence.
Answer option D is incorrect. A communications matrix simply maps which stakeholder need to communicate with other stakeholders.

Question 33

Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?

Correct Answer:C
The to-complete performance index can be found by using the formula (BAC-EV)/(BAC- AC) for a value of 1.07. The higher the value is from 1, the less likely the project will meet the BAC.
To-complete Performance Index (TCPI) is the measured projection of the anticipated performance required to achieve either the BAC or the EAC.
TCPI indicates the future required cost efficiency needed to achieve a target EAC (Estimate At Complete).Once approved, the EAC supersedes the BAC as the cost performance goal. Any significant difference between TCPI and the CPI needed to meet the EAC should be accounted for by management in their forecast of the final cost. The formula for TCPI is as follows:
TCPI = {(BAC-EV)/(BAC-AC)}
Answer option A is incorrect. 0.98 is the project's cost performance index. Answer option D is incorrect. This is the project's schedule performance index.
Answer option B is incorrect. -$16,667 is the project's variance at completion.

Question 34

You are the project manager for your organization. You have created the project schedule and have presented it to the management for their approval. Management decides to enforce resource leveling heuristics on your project schedule. What will likely happen to your project now?

Correct Answer:C
Resource leveling heuristics limits the amount of time a resource is allowed to work in a given time period. This action typically increases the project duration. By adding additional resources to effort-driven activity the project can still complete, often, in the same schedule, otherwise the duration of the project will increase.
Answer option B is incorrect. Resource leveling heuristics does not change the project scope.
Answer option A is incorrect. This is not an instance of cutting the project scope. Answer option D is incorrect. The project scope baseline is not affected by resource leveling heuristics.

Question 35

You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

Correct Answer:D
The schedule baseline is a specific version of the project schedule developed from the schedule network analysis. It is built by networking individual work elements and verifying the path or paths with the longest total duration. That path is then compared against the project due date, or it may serve as the determinant of the project end date. Schedule baseline is a project schedule used in measuring project progress. It helps provide a comparison with the actual progress of work against the schedule and to determine if performance to date is within acceptable parameters. Any change caused by change in scope of the project invalidates the original schedule and requires a new baseline schedule.
Answer option A is incorrect. Management may impose constraints on the project, but according to the PMI, the baseline is developed from schedule network analysis.
Answer option B is incorrect. Constraints on the project typically include time, cost, and scope (among others), but the schedule baseline is only concerned with the time limits of the project.
Answer option C is incorrect. Project stakeholders are those entities within or without an organization, which: Sponsor a project or, Have an interest or a gain upon a successful completion of a project. Examples of project stakeholders include the customer, the user group, the project manager, the development team, the testers, etc. Stakeholders are anyone who has an interest in the project. Project stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion. They may also exert influence over the project's objectives and outcomes. The project management team must identify the stakeholders, determine their requirements and expectations, and, to the extent possible, manage their influence in relation to the requirements to ensure a successful project.