Question 131

- (Topic 2)
What defines the portion of work included in a contract for items being purchased or acquired?

Correct Answer:D

Question 132

- (Topic 2)
A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

Correct Answer:A

Question 133

- (Topic 3)
A project manager requesting industry groups and consultants to recommend project intervention is relying on:

Correct Answer:C

Question 134

- (Topic 5)
Which of the following is a measure of the value of work completed compared to the actual cost or progress made on the project?

Correct Answer:B

Question 135

- (Topic 5)
Lessons learned are created and project resources are released in which Process Group?