- (Topic 3)
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
Correct Answer:C
- (Topic 3)
A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?
Correct Answer:C
- (Topic 4)
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?
Correct Answer:C
- (Topic 4)
Administer Procurements is part of which Process Group?
Correct Answer:C
- (Topic 4)
Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?
Correct Answer:D