Question 146

- (Topic 3)
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

Correct Answer:B

Question 147

- (Topic 3)
Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?

Correct Answer:B

Question 148

- (Topic 3)
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Correct Answer:B

Question 149

- (Topic 2)
The following is a network diagram for a project.
PMP dumps exhibit
How many possible paths are identified for this project?

Correct Answer:B

Question 150

- (Topic 4)
Which tool or technique is used in the Perform Integrated Change Control process?

Correct Answer:D