- (Topic 2)
The following is a network diagram for a project.
What is the critical path for the project?
Correct Answer:A
- (Topic 4)
Market conditions and published commercial information are examples of which input to the Estimate Costs process?
Correct Answer:C
- (Topic 3)
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
Correct Answer:D
- (Topic 3)
Which technique is used in Perform Quantitative Risk Analysis?
Correct Answer:A
- (Topic 4)
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
Correct Answer:B