- (Exam Topic 2)
Which process provides information for the project board to review a completed stage and confirm continued business justification?
Correct Answer:D
Reference https://www.prince2.com/uk/prince2-processes
- (Exam Topic 2)
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
Correct Answer:C
Reference
http://prince2.wiki/Directing_a_Project
- (Exam Topic 2)
Within which integrated element does PRINCE2 set minimum requirements?
Correct Answer:A
- (Exam Topic 2)
What should the benefits management approach define?
Correct Answer:C
- (Exam Topic 2)
Which is a difference between management and technical stages?
Correct Answer:B