- (Exam Topic 2)
What action is taken as part of the 'controlling a stage' process?
* 1. Create an exception plan
* 2. Authorize work to be done
* 3. Take corrective action
* 4. Obtain approvals for completed products
Correct Answer:B
Reference
https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage-process-in-p
- (Exam Topic 2)
Which is a purpose of the Risk Register?
Correct Answer:B
- (Exam Topic 2)
What information should be recorded in the quality register?
Correct Answer:C
Reference https://mplaza.pm/prince2-quality-register-template/
- (Exam Topic 2)
Which is one of the three levels of plan in PRINCE2?
Correct Answer:C
- (Exam Topic 2)
What should the 'managing product delivery' process ensure?
* 1. That the planned products meet their quality criteria
* 2. That the stage plan is kept up to date
* 3. That the project board is provided with progress information
* 4. That the planned products are delivered within tolerance
Correct Answer:C
Reference
http://prince2.wiki/Managing_Product_Delivery