Question 6

In accordance with Scrum theory, how should a group of 100 people be divided into multiple
Scrum Teams?
(choose the best answer)

Correct Answer:C
In accordance with Scrum theory, a group of 100 people should be divided into multiple Scrum Teams by understanding the product, the product vision and the rules of the Scrum framework, and then dividing themselves into teams because:
✑ It respects the self-organization and empowerment of the people. The people are the ones who have the knowledge, skills, and experience to create and deliver the product. They are also the ones who will work together as Scrum Teams, collaborating and coordinating their efforts. Therefore, they should have the autonomy and authority to decide how to form their teams, based on their preferences, interests, and capabilities.
✑ It supports the alignment and coherence of the Scrum Teams. The people should have a clear and shared understanding of the product, the product vision, and the rules of the Scrum framework before forming their teams. This can help them to align their goals and missions, to ensure that they are working on the same product and towards the same vision. It can also help them to follow the same principles and practices of Scrum, to ensure that they are working effectively and consistently.
✑ It fosters the collaboration and synergy of the Scrum Teams. The people should form their teams in a way that maximizes their collaboration and synergy. This can mean choosing team members that complement each other’s skills and strengths, that have good rapport and trust, that can communicate and coordinate well, and that can deliver a valuable Increment each Sprint.
References:
✑ Scrum Guide 2020, page 5: “Scrum Teams are cross-functional, meaning the members have all the skills necessary to create value in each Sprint.”
✑ Scrum Guide 2020, page 5: “Scrum Teams are self-managing, meaning they internally decide who does what, when, and how.”
✑ Scrum Guide 2020, page 9: “Multiple Scrum Teams working together on a product use one Product Backlog.”
✑ Scrum Guide 2020, page 9: “The Product Owner is one person, not a committee.”

Question 7

True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.

Correct Answer:B
✑ False: Product Owners do not have to specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.
✑ Acceptance criteria are a set of conditions that a Product Backlog item must satisfy to be considered “Done” and acceptable for delivery.
✑ Acceptance criteria are not mandatory in Scrum, but they can help the Product Owner and the Developers to clarify the expectations and requirements of a Product Backlog item.
✑ Acceptance criteria can be added or refined by the Product Owner at any time, but they should be clear and testable before the Sprint starts.
✑ The Developers can select a Product Backlog item in Sprint Planning based on their understanding of its value, scope, and complexity, as well as their capacity and skills. They can also collaborate with the Product Owner to define or refine the acceptance criteria during Sprint Planning. References: Scrum Guide, Section 3.4 (The Product Backlog), Section 5.1 (Sprint Planning), and Section 6.4 (The Increment)

Question 8

You are the Scrum Master of a new, to be developed Product. Development is going to require 45 people. What is a good first question for you to suggest the group thinks about when forming into teams?
(choose the best answer)

Correct Answer:D
When forming a Scrum team, it is important to ensure that the team has all the skills and knowledge necessary to deliver a working product12. The Scrum team should be cross-functional and self-managing, without relying on external experts or team leads34. Therefore, the question of how to make sure all teams have the right amount of expertise is a good first question to consider when forming into teams.

Question 9

Why do the Developers need a Sprint Goal? (choose the best answer)

Correct Answer:C
The Developers need a Sprint Goal because it gives them a common yet specific goal to focus on during the Sprint. This is because:
✑ The Sprint Goal is a short-term objective that provides guidance and focus to the Scrum Team throughout the Sprint. It is a flexible and negotiable commitment that can be adjusted as more is learned throughout the Sprint.
✑ The Developers are accountable for creating a “Done” Increment in every Sprint.
They must ensure that every Product Backlog item they work on meets the Definition of Done before it is considered complete.
✑ The Developers are self-managing professionals who organize and manage their own work. They decide how to best accomplish their work, rather than being directed by others outside the Scrum Team.
✑ The Developers need a Sprint Goal to align their efforts and collaborate effectively as a team. The Sprint Goal helps them prioritize and optimize their work based on value and impact. The Sprint Goal also helps them cope with uncertainty and complexity by providing a clear direction and a shared purpose.
Other options, such as a Sprint Goal only giving purpose to Sprint 0, Sprint Goals being not valuable, or a Sprint Goal ensuring that all of the Product Backlog items selected for the Sprint are implemented, are not valid reasons why the Developers need a Sprint Goal. They may reflect a misunderstanding of what a Sprint Goal is or how Scrum works. References:
✑ [Scrum Guide], page 15, section “Sprint Goal”
✑ [Scrum Guide], page 7, section “Developers”
✑ [Scrum Guide], page 10, section “Definition of Done”
✑ [Scrum Guide], page 10, section “Increment”

Question 10

In order to maximize the value of the product, a Product Owner needs awareness of the following: (choose the best answer)

Correct Answer:E
In order to maximize the value of the product, a Product Owner needs awareness of the following:
✑ Competitive research. The Product Owner should be aware of the competitive landscape and the market trends that affect the product. They should know who are the competitors, what are their strengths and weaknesses, how do they differentiate themselves, and what are their strategies and goals. This can help the Product Owner to identify opportunities, threats, and gaps in the market, and to position the product accordingly.
✑ Customer feedback. The Product Owner should be aware of the customer needs, preferences, expectations, and satisfaction with the product. They should collect and analyze feedback from various sources, such as surveys, interviews, reviews, analytics, etc. This can help the Product Owner to validate assumptions, test hypotheses, measure outcomes, and discover insights that can inform the product decisions and priorities.
✑ Product vision. The Product Owner should be aware of the product vision, which is a clear and compelling statement of the desired future state of the product. The product vision describes the purpose, value proposition, target audience, and key features of the product. It also aligns with the organizational vision and mission. This can help the Product Owner to communicate and inspire the stakeholders, to guide and focus the Scrum Team, and to evaluate and adjust the product direction.
✑ Forecasting & feasibility. The Product Owner should be aware of the forecasting and feasibility of the product. They should estimate and plan the scope, time, cost, quality, and risk of delivering the product. They should also assess the technical, operational, legal, ethical, and social feasibility of developing and releasing the product. This can help the Product Owner to optimize the value of the work of the Scrum Team, to manage expectations and dependencies, and to handle uncertainties and changes.
References:
✑ Scrum Guide 2020, page 6: “The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team.”
✑ Scrum Guide 2020, page 11: “The Product Goal describes a future state of the product which can serve as a target for the Scrum Team to plan against.”
✑ Scrum Guide 2020, page 11: “The Product Owner is accountable for effective Product Backlog management, which includes … optimizing the value of the work the Scrum Team performs.”