Question 51

Portfolio managers tend to use the efficient frontier analysis as a modeling approach that gives decision makers the analytical tool to optimize portfolios given resource constraints such as risk. Consider that your company is risk-averse, on which side of the efficient frontier curve should the undertaken portfolios lie?

Correct Answer:B

Question 52

Portfolios include a lot of work and as a portfolio manager you need to keep an eye on the value realization while maintaining the strategic alignment. You are currently aggregating value delivered by the portfolio components. What can you use to help you in this context?

Correct Answer:A

Question 53

During the portfolio lifecycle, components will be authorized, initiated, executed and closed accordingly. For authorizing the portfolio, as a program manager you will use which of the Which of the following tools and techniques?

Correct Answer:B

Question 54

Working to best optimize resource supply and demand in your telecom company, authorized components are prioritized to help in resource allocation. This means as you work to do so, you need to review the portfolio because:

Correct Answer:B

Question 55

Your company has had a portfolio management process in place for five years at the enterprise level, in its business units, and even in its complex programs. This year the company's Center for Excellence received an award for its work in this area from PMIĀ®. As the Portfolio Manager, you have predefined metrics in place, which are critical because:

Correct Answer:D