Question 71

One of your company's junior portfolio managers came to you for advice. He noticed while checking the roadmap that it does not include all the portfolio components. What should be your advice to him?

Correct Answer:B

Question 72

Having worked in portfolio management before, you are pleased you were selected to implement it and be the portfolio manager for your motorcycle company, well known throughout the world. As it is a new function, you worked with the Enterprise Program Management Office to ensure you had a complete inventory of the work in progress. Now as you prepared your various portfolio management artifacts, and have a Portfolio Review Board meeting upcoming in two weeks, sponsors will be proposing new components. This means:

Correct Answer:A

Question 73

As you work to determine which of four possible components to optimize the portfolio, assume you are using the internal rate of return as the key crite rion to make your recommendation. Only one new component can be added based on financial constraints. Each of the four potential components has benefits that support the strategic plan. Based on the following data, you recommend:
PfMP dumps exhibit

Correct Answer:C

Question 74

Specific types of communication technology that are used such as communication media, record retention policies, and security information are examples of:

Correct Answer:B

Question 75

A portfolio manager needs to continuously balance the need and requirements with the available resources and needs to maintain a balanced portfolio and portfolio resources in order to optimize delivery. For this, you are always on the lookout to optimize your portfolio. What can you use to start this process?

Correct Answer:B