You are managing a portfolio in a functional organization and resources are shared between operations and projects. You are continuously performing capability and capacity analysis in order to optimize the portfolio. Which of the following capability and capacity analysis is used to limit the number OR size of components the organization can execute?
Correct Answer:B
A portfolio includes a lot of independent components with the same strategic aim. As a portfolio manager you will need to preare a qualified list of components to be used to reach the strategic goals and objectives. What input can you use in order to define the mix of portfolio components?
Correct Answer:C
You are currently using a Comparative Advantage Analysis and conducting a what-if analysis to consider how the portfolio component and its intended benefits could be achieved by various options, including resource capability and capacity mix. In which process are you currently working?
Correct Answer:C
All measurements in a Portfolio are done in correspondence to Key Performance Indicators (KPIs), and defining those KPIs is essential and should be done by highly capable personnel. Which of the following is true regarding who prepares KPIs and which party approves them?
Correct Answer:C
After the stakeholder analysis is complete, a best practice is to put stakeholders into a matrix to develop a communications management strategy. A simple but useful approach is to set it up to show:
Correct Answer:D