Question 116

Communication requirements are analyzed and documented in the portfolio communication management plan to be used by other processes as needed. Which of the processes use this information in order to provide accurate information in a timely manner?

Correct Answer:B

Question 117

Chartering the portfolio is an important step towards the initiation of the endeavor. It authorizes the portfolio managers to use the resources and marks the first step towards the allocation of resources to the components upon their initiation. Which of the below can help you while developing the charter?

Correct Answer:C

Question 118

As a result of optimization, one of the components was deemed necessary to be terminated. One of the executive managers found about this and called you telling you that you should leave this component as it is of interest to her and she wants to see it finalized and that she will make resources available to it if needed. What should be your best course of action?

Correct Answer:C

Question 119

CORRECT TEXT
As you prepare a list of possible components for your railroad to consider since most of its programs and projects are large and complex, your management team has suggested in your analysis of which components to pursue that you conduct statistical simulations of budgets, schedules, and resource allocations. You therefore decide to use:

Correct Answer:C

Question 120

During the portfolio lifecycle, you will be using the roadmap a lot and you be using it to report progress to different stakeholders. When it comes to portfolio roadmap, which of the following options is true?

Correct Answer:B