A big strategic change occurred at the organization level and has impacted multiple portfolios in the organization including yours. The CEO has asked you to prepare a presentation to depict the impact of this change on portfolio resources. Which of the following should you present in this case?
Correct Answer:B
In your web app company, the portfolio is constantly changing. It is not unusual for a new proposal to be submitted each day and for other components to be terminated as a competitor was first to market. The Portfolio Review Board usually meets daily in this fast- paced environment as it:
Correct Answer:D
You have scored the portfolio components and are analyzing the data in order to prioritize the components. Using the following scoring table, which of the options represents the correct Components Priority? Taking into consideration that the costs for each component is Component A: 10 K USD, Component B: 15 K USD, Component C: 16 K USD, Component D: 13 K USD and Component E: 11 K USD; The budget for this portfolio is a fixed one of 40 k USD Larger image
Correct Answer:D
Portfolios include a lot of work and as a portfolio manager you need to keep an eye on the value realization while maintaining the strategic alignment. You are currently aggregating value delivered by the portfolio components. Which of the following methods are helpful to you?
Correct Answer:D
Assuming a portfolio manager position means one has more stakeholders than in program, project, or operational roles. The goal is to identify all interested stakeholders but often overlooked are:
Correct Answer:D