Question 21

One of your component managers has submitted his resignation and left the company; a new program manager joins the portfolio replacing him. Which document you use to inform the new program manager about his responsibilities in the portfolio?

Correct Answer:C

Question 22

Resources allocation and optimization for use is key to a successful portfolio. You have assigned human resources, funds and other required assets to a component that you have initiated recently. What should have been done prior to being able to to that?

Correct Answer:D

Question 23

For years, your aerospace company has been a leader in the development of sophisticated avionic hardware systems around the world. The executives want to continue with this well- recognized product line, but also they decided it is time to move into state-of-the art software to complement the hardware products. You have been asked to assess whether there are skill set limitations in the company to assess resource capacity internally. To do so, you decide to:

Correct Answer:A

Question 24

Assume you are creating a roadmap for your portfolio and will present it to key stakeholders and then to the Portfolio Review Board. You realize you will be adding additional detail to it, but you also believe its graphical format will be useful. In developing it, you decide to reference prioritization, dependencies, and organizational areas so you should consult the:

Correct Answer:C

Question 25

You have already created portfolio scenarios (what-if analysis) by reviewing components against prioritization criteria and using analysis techniques (e.g., options analysis, risk analysis, SWOT analysis, financial analysis). You now want to recommend portfolio scenario(s) and related components, based on prioritization analysis/criteria. You are doing this in order to

Correct Answer:D