Free PgMP Exam Dumps

No Installation Required, Instantly Prepare for the PgMP exam and please click the below link to start the PgMP Exam Simulator with a real PgMP practice exam questions.
Use directly our on-line PgMP exam dumps materials and try our Testing Engine to pass the PgMP which is always updated.

  • Exam Code: PgMP
  • Exam Title: Program Management Professional (PgMP)
  • Vendor: PMI
  • Exam Questions: 452
  • Last Updated: December 18th,2024

Question 1

- (Topic 1)
A project manager in your program has estimated the cost of a program to be $145,000. As the project manager's project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project's deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?

Correct Answer:A

Question 2

- (Topic 3)
After program closure, the lessons learned document becomes the part of ?

Correct Answer:B

Question 3

- (Topic 1)
What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

Correct Answer:D

Question 4

- (Topic 3)
You are the program manager for your organization and you're dealing with several issues about the materials used in the program. Right now, the issues have been assigned to issue owners for resolution in ten days. In the interim, what should you do with the issues?

Correct Answer:A

Question 5

- (Topic 4)
You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

Correct Answer:C