- (Topic 2)
Which one of the following is the best definition of program quality?
Correct Answer:A
- (Topic 4)
You are the program manager for your organization and management has asked you to be certain to finalize the lessons learned documentation for your program. When will the lessons learned documentation be created?
Correct Answer:B
- (Topic 3)
Martha is the program manager for her organization. One of the projects of a program is
done but is also considerably over budget. Kay, the project manager, has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Martha instruct Kay to do with the information regarding the schedule delays and cost overruns?
Correct Answer:A
- (Topic 1)
You are the program manager of the GHY Program in your organization. It has come to your attention that some of the project managers in your program are adding time to each project activity in an effort to pad their durations in case some event happens in their project that will cause delays. What principle should you share with these project managers that counterattack the concept of padding activities with additional time?
Correct Answer:A
- (Topic 2)
A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?
Correct Answer:C