Question 1

What are the minimum requirements for a Feature?

Correct Answer:B
The minimum requirements for a feature are a name, a benefit hypothesis, and acceptance criteria12. A name is a brief and descriptive phrase that summarizes the feature. A benefit hypothesis is a statement that describes the expected outcome and value of the feature for the customer or user. Acceptance criteria are a set of conditions that the feature must satisfy to be accepted by the customer or stakeholder12. Some additional information that might be helpful for you are:
•The other options (A, C, and D) are not the minimum requirements for a feature, but rather additional or optional elements that may be included in the feature definition.
•Data models are representations of the data structures and relationships that the feature requires or affects. Data models are not mandatory for a feature, but they may be useful for complex or data-intensive features3.
•Priority is the relative importance or urgency of a feature compared to other features. Priority is not a requirement for a feature, but it is a factor that influences the feature selection and sequencing4.
•Non-functional requirements (NFRs) are system qualities that guide the design of the solution and often serve as constraints across the relevant backlogs. NFRs are not specific to a feature, but they may affect the feature implementation or testing5.
•Architecture is the design and structure of the system that supports the solution. Architecture is not a requirement for a feature, but it is an enabler that facilitates the feature delivery.

Question 2

Which of the following statements is one of the five Lean Thinking principles?

Correct Answer:C
Identifying the Value Stream for each product is one of the five Lean Thinking principles proposed by Womack and Jones in 1996. A value stream is the sequence of activities that deliver value to the customer, from the initial request to the final delivery1. Identifying the value stream for each product helps to eliminate waste, optimize flow, and increase customer satisfaction2.
References:
•The Five Principles of Lean - Project Management Institute
•Value Streams - Scaled Agile Framework

Question 3

Which is developed by teams and rolled up to the ART level during PI Planning?

Correct Answer:C
Objectives are developed by teams and rolled up to the ART level during PI Planning. Objectives are a summary of the business and technical goals that the teams and the ART intend to achieve in the upcoming Program Increment (PI)1. During PI Planning, each team creates their own team PI objectives, which are then presented and reviewed by the ART and the stakeholders2. The aggregated team PI objectives form the ART PI objectives, which provide a common vision and alignment for the ART3.
References:
•PI Objectives - Scaled Agile Framework
•PI Planning - Scaled Agile Framework

Question 4

What is included in the Inspect and Adapt agenda?

Correct Answer:C
The Inspect and Adapt (I&A) agenda in the Scaled Agile Framework (SAFe) is a significant event at the end of each Program Increment (PI), focusing on continuous improvement and adjustment in Agile processes. It comprises three main parts:
* 1. PI System Demo: This is the first part of the I&A event, intended to showcase all the features developed by the Agile Release Train (ART) over the course of the PI. It typically includes a broader audience and is more formal than regular system demos. Business Owners collaborate with each Agile team to score the actual business value achieved for their Team PI Objectives.
* 2. Quantitative and Qualitative Measurement: This part involves the collective review of quantitative and qualitative metrics agreed upon by the teams. This review is aimed at discussing data and trends to measure the team's performance. Important metrics like the programpredictability measure are also analyzed, with each team's planned vs. actual business value contributing to this measure.
* 3. Retrospective and Problem-Solving Workshop: This structured session allows teams to reflect on their performance, identify areas of improvement, and create action plans. It includes identifying improvements, conducting root cause analysis using tools like the "5 Whys" or fishbone diagrams, brainstorming solutions, prioritizing actions, and creating detailed action plans for implementation.
The I&A event promotes continuous improvement, enhanced agility, increased transparency, higher quality outcomes, better decision-making, improved employee engagement, and alignment with organizational goals.
It's essential for both Agile Release Trains and Solution Trains to effectively inspect and adapt their processes for optimal performance and continuous improvement.
References:
•Scaled Agile Framework: Inspect and Adapt.
•Dee Project Manager: SAFe Inspect and Adapt: Supercharge Agile Excellence.

Question 5

What is the primary purpose of PO Sync?

Correct Answer:A
The primary purpose of PO Sync is to assess progress of the Program Increment (PI) and adjust scope and priority as needed12. PO Sync is a regular event that involves the Product Owners from all the Agile teams in an Agile Release Train (ART)12. In PO Sync, they share the status of their work, identify dependencies, risks, and impediments, and align on the product vision and roadmap12. PO Sync helps to ensure that the ART delivers value to the customers and meets the PI objectives12.
Some additional information that might be helpful for you are:
•The other options (B, C, and D) are not the primary purpose of PO Sync, but rather purposes of other events or activities.
•Building PI Objectives and improving alignment is the purpose of PI Planning, which is a two-day event that occurs at the beginning of each PI3. In PI Planning, all the members of the ART collaborate to define, prioritize, and plan the work for the next PI3.
•Aligning with Coach Sync participants on the status of the PI is the purpose of Scrum of Scrums (SoS), which is a regular event that involves the Scrum Masters from all the Agile teams in an ART4. In SoS, they coordinate and synchronize the work of the teams, resolve cross-team impediments, and report the progress and risks to the RTE4.
•Conducting backlog refinement is an activity that occurs throughout the PI, where the Product Owner and the Development team review and update the Team Backlog to prepare for the upcoming Iterations. Backlog refinement helps to ensure that the work items are clear, feasible, and valuable